CONOPS A product of CONOPS
Implementation

Phased, with an exit gate you can see coming

A first site of CONOPS | MOS (Manufacturing Operating System) goes live in about eight to ten weeks from the discovery kickoff. Each phase has deliverables, a duration, the hours we need from your people and criteria that must be true before the next phase starts.

Phase 1 · 2 weeks

Discovery

Deliverables

  • Site, role and ERP inventory
  • Record-type catalogue with fields, priorities and SLAs
  • Spreadsheet inventory: what gets replaced, what stays
  • Fixed-scope statement of work
Who we need from you
  • Executive sponsor 2 h
  • Operations lead 8 h
  • Engineering/quality lead 4 h
  • IT 2 h, DBA 1 h, Compliance 2 h
Exit criteria
  • Statement of work signed
  • Deployment option chosen
  • Named owners for every phase
Phase 2 · 2 to 3 weeks

Configuration

Deliverables

  • Sites, departments, workcenters and shift calendars
  • Categories, priorities, SLAs and response plans
  • Roles assigned; modules switched per site
  • Dev environment your leads can click through
Who we need from you
  • Operations lead 8 h
  • Engineering/quality lead 4 h
  • IT 4 h, DBA 2 h
Exit criteria
  • Lead walkthrough signed off
  • Permission grid reviewed by compliance
  • Kiosk form tested at the cell
Phase 3 · 2 to 4 weeks per ERP

Integration

Deliverables

  • Linked server and service account
  • Load definitions for each dataset
  • Dataset validation against ERP reports
  • Verify reports and nightly schedule
Who we need from you
  • IT 6 h
  • DBA 8 h
  • Operations lead 2 h
  • Finance 2 h for reconciliation
Exit criteria
  • Nightly load running for five consecutive nights
  • Row counts and totals reconciled to the ERP
  • Verify reports green
Phase 4 · 1 to 2 weeks

Workflow design

Deliverables

  • Three templates designed in workshops
  • Queues, outcomes, scheduling and escalation set
  • Auto-launch rules by record category
  • Templates tested end to end in staging
Who we need from you
  • Engineering/quality lead 8 h
  • Operations lead 6 h
  • Contracts 2 h where templates touch customers
Exit criteria
  • Each template run once by its real owners
  • Ledger export reviewed
  • Templates versioned with effective dates
Phase 5 · 30 days

Go-live and hypercare

Deliverables

  • Training by role, 45 minutes each
  • Kiosk terminals set up and labelled
  • Production cut-over with the migration manifest
  • Daily 15-minute check-ins for 30 days
Who we need from you
  • Operations lead 10 h
  • Engineering/quality lead 6 h
  • IT 4 h, DBA 2 h
  • All users 45 min
Exit criteria
  • Adoption: records submitted per day by site
  • Open issues at zero or owned with a date
  • Support plan active
Additional sites reuse the configuration workbook and the load definitions. A second site on the same ERP typically adds two to three weeks; a second ERP adds its own integration phase.