Implementation
Phased, with an exit gate you can see coming
A first site of CONOPS | MOS (Manufacturing Operating System) goes live in about eight to ten weeks from the discovery kickoff. Each phase has deliverables, a duration, the hours we need from your people and criteria that must be true before the next phase starts.
Phase 1 · 2 weeks
Discovery
Deliverables
- Site, role and ERP inventory
- Record-type catalogue with fields, priorities and SLAs
- Spreadsheet inventory: what gets replaced, what stays
- Fixed-scope statement of work
Who we need from you
- Executive sponsor 2 h
- Operations lead 8 h
- Engineering/quality lead 4 h
- IT 2 h, DBA 1 h, Compliance 2 h
Exit criteria
- Statement of work signed
- Deployment option chosen
- Named owners for every phase
Phase 2 · 2 to 3 weeks
Configuration
Deliverables
- Sites, departments, workcenters and shift calendars
- Categories, priorities, SLAs and response plans
- Roles assigned; modules switched per site
- Dev environment your leads can click through
Who we need from you
- Operations lead 8 h
- Engineering/quality lead 4 h
- IT 4 h, DBA 2 h
Exit criteria
- Lead walkthrough signed off
- Permission grid reviewed by compliance
- Kiosk form tested at the cell
Phase 3 · 2 to 4 weeks per ERP
Integration
Deliverables
- Linked server and service account
- Load definitions for each dataset
- Dataset validation against ERP reports
- Verify reports and nightly schedule
Who we need from you
- IT 6 h
- DBA 8 h
- Operations lead 2 h
- Finance 2 h for reconciliation
Exit criteria
- Nightly load running for five consecutive nights
- Row counts and totals reconciled to the ERP
- Verify reports green
Phase 4 · 1 to 2 weeks
Workflow design
Deliverables
- Three templates designed in workshops
- Queues, outcomes, scheduling and escalation set
- Auto-launch rules by record category
- Templates tested end to end in staging
Who we need from you
- Engineering/quality lead 8 h
- Operations lead 6 h
- Contracts 2 h where templates touch customers
Exit criteria
- Each template run once by its real owners
- Ledger export reviewed
- Templates versioned with effective dates
Phase 5 · 30 days
Go-live and hypercare
Deliverables
- Training by role, 45 minutes each
- Kiosk terminals set up and labelled
- Production cut-over with the migration manifest
- Daily 15-minute check-ins for 30 days
Who we need from you
- Operations lead 10 h
- Engineering/quality lead 6 h
- IT 4 h, DBA 2 h
- All users 45 min
Exit criteria
- Adoption: records submitted per day by site
- Open issues at zero or owned with a date
- Support plan active
Additional sites reuse the configuration workbook and the load definitions. A second site on the same ERP typically adds two to three weeks; a second ERP adds its own integration phase.
Next step
See CONOPS | MOS running on your data, in your environment.
A 45-minute discovery call with the people who built it. We cover your sites, your ERP, your approval paper and which deployment fits your compliance posture.